This petition for leave to appeal arose from the dismissal of an execution application filed by the House Building Finance Corporation of Pakistan. The application to execute a decree dated 8-3-1997 was filed on 14-10-2000 and was dismissed as time-barred by the Additional District Judge, Jhang, a decision subsequently upheld in appeal by the Lahore High Court. The core legal question was whether the limitation period for filing a first application for execution of a decree is three years under Article 181 of the Limitation Act 1908 or six years under Section 48 of the Code of Civil Procedure 1908. The Supreme Court affirmed the lower court's decisions and refused leave to appeal. Reaffirming established precedent, the Court held that the limitation period for making a first execution application is three years as governed by Article 181 of the Limitation Act 1908. Section 48 of the Code of Civil Procedure 1908 applies only to fresh execution applications after the initial application has been disposed of.
- What is the limitation period for filing a first application for execution of a decree?
- Does Section 48 of the Code of Civil Procedure 1908 apply to a first execution application?
- Which statutory provision governs the limitation period for a first application to execute a civil decree?
- Section 48, Code of Civil Procedure 1908
- Article 181, Limitation Act 1908
' FAQIR MUHAMMAD KHOKHAR, J.--- The petitioner filed an application for the execution of decree dated 8-3-1997 on 14-10-2000 which was dismissed, as barred by time, by order dated 15-6-2001, passed by the Additional District Judge, Jhang. The F.A.O. No,181 of 2001 of the petitioner was also dismissed by a learned Single Judge of the Lahore High Court, Lahore vide impugned order, dated 19-6-2002. Hence this petition for leave to appeal.
2. The learned counsel for the petitioners argued that the execution of the decree passed in favour of the petitioners ought not have been refused merely on a technical point of limitation and that even otherwise, the period of limitation for such-like applications was six years and not three years as provided by section 48, C.P.C.
3. We have heard the learned counsel for the petitioner at some length and have also perused the available record. We find that the controversy involved in the present case has already been set at rest by this Court in the case of Mahboob Khan v. Hassan Khan Durrani PLD 1990 SC 778, wherein it was held that for making first application for execution of a decree a period of three years was provided in terms of Article 181 of the Limitation Act and that the provisions of section 48, C.P.C.
Could be availed only in the case of fresh application, once the first application had been disposed of. In our view, the impugned order of the High Court is in conformity with the law laid down by this Court to which no exception can be taken.
4. For the foregoing reasons, we do not find any merit in this petition which is dismissed and leave to, appeal is refused accordingly.
Cited by 12 cases
- National Highway Authority Versus Ghulam Ali 2025 MLD 1075
- Chaudhary MUHAMMAD UMAR Versus IMRAN SAEED 2026 CLC 1092
- Chaudhary MUHAMMAD UMAR Versus HAMID SAEED 2026 CLC 880
- Haji Mir Badshah and others vs District Officer, Revenue & Estate/Land 2024 PHC 170, 2024 PLJ Peshawar 113
- Rabnawaz vs Mst. Sabu Bibi & others 2022 PHC 410
- Rabnawaz vs Mst. Sabu BIBI and others 2023 PLJ Peshawar 49
- RABNAWAZ Versus Mst. SABU BIBI 2023 PLD 19
- Karam Shah & others vs Provincial Secretary Forest KPK & others 2020 CLC 1085, 2019 PHC 330
- Muhammad Usman vs Amanullah and 15 others 2020 YLR 979
- SAEEDA SALAHUDDIN Versus Flight Lt. (Retd.) FAROUK AZIZ EFFENDI (LATE) 2020 CLCN 40
- ATTA ULLAH and 2 others vs AKBAR 2014 YLR 1034
- National Highway Authority etc vs Ghulam Ali (deceased) through legal 2025 LHC 1376, 2025 PLJ Lahore 587