Pakistan Case Law
1980 SCMR 588

MUHAMMAD AREF EFFENDI vs EGYPT AIR

⭐ Prefer in Google
Citation1980 SCMR 588
CourtSupreme Court of Pakistan
Case No.Civil Appeal No, 10 of 1950 in Civil Petition for Special Leave to Appeal No, K-
Date1980-03-02
Judge(s)Muhammad Haleem, G. Safdar Shah and Karam Elahee Chauhan
Authored byKaram Elahee Chauhan
ResultAppeal allowed
AI Summary — generated from this judgment; read the full text below and verify before relying on it.

The petitioner, an agent for the respondent airline, filed a civil suit challenging the termination of his agency agreement and sought a temporary injunction to maintain the status quo pending the suit's outcome. The High Court dismissed the application, holding that the agent lacked a sufficient interest in the subject matter to warrant an injunction. Upon appeal, the Supreme Court observed that the case involved substantial questions of law and fact, including the circumstances under which an agency contract may be revoked and the applicability of Section 202 of the Contract Act 1872. The Court held that given the complexity of the issues, which required a thorough examination of evidence, the High Court was not justified in refusing the temporary injunction. Consequently, the Supreme Court granted the injunction on specific terms, requiring the rendering of accounts and the provision of bank guarantees by both parties to protect their respective interests, while emphasizing that these interim measures did not constitute a final opinion on the merits of the pending suit.

Questions settled in this judgment
  • Under what circumstances can a contract of agency be cancelled or revoked by a principal?
  • Whether Section 202 of the Contract Act 1872 is applicable to a specific agency termination dispute?
  • Is a plaintiff entitled to a temporary injunction to maintain the status quo in an agency dispute pending the trial of the suit?
Laws & provisions referred
  • Section 202, Contract Act 1872
temporary injunctionagency contracttermination of agencystatus quospecial leave to appealinterim relief

ORDER

' KARAM ELAHEE CHAUHAN, J.-The petitioner (hereinafter called the Agent) is holding a general sale agency of the respondent airline namely Egypt Air (a company incorporated and functioning under the laws of Arab Republic of Egypt. The terms of the agency are contained in an agreement dated 29-1-1973 (copy placed on record).

2. The principal terminated the agency of the petitioner with effect from 31-12-1979 to challenge which the petitioner filed a civil suit which is still pending on the original side of the Sind High Court at Karachi.

3. In the aforesaid suit the petitioner agent claimed a temporary injunction to maintain the status quo so as to continue the agency business till the decision of the suit. A learned Single Judge of the High Court dismissed the application on 16-2-1980, holding that the petitioner agent had no interest in the subject-matter of the suit and as such his agency could not be retained by means of temporary injunction.

4. The plaintiff/petitioner has come up in a petition for special leave to appeal against the same to this Court. We have heard the learned counsel for the parties and from their arguments as also after going through the judgment under appeal, we notice that the case involves substantial questions of law and fact namely:-

(i) under what circumstances a contract of agency of the kind involve in this case could be cancelled or revoked by a principal;

(ii) whether section 202 of the Contract Act was applicable to the fact of this case and what is true construction and scope of that section.

(iii) whether the plaintiff/petitioner is entitled to continue the agency an or claim damages from the principal on the pleadings as made by hi in his plaint and if so to what ultimate relief he will be entitled on the facts and in the overall circumstances of the case.

(iv) whether the plaintiff/petitioner had not submitted his account to the principal in terms of the contract and whether he was justified in with holding the same on any legal ground; and

(v) whether the termination of contract in this case was lawful or not.

5. These are all substantial questions of law and fact and since the involve a careful study and scrutiny after leading of appropriate evidence therefore the High Court was not justified to refuse grant of a temporary injunction as prayed for at this stage. In the circumstances we are inclined to grant leave to appeal to the petitioner and converting this petition into an apeal accept the same and hold that this was a fit case in which a temporar injunction ought to have been granted on terms.

7. Consequently we grant a temporary injunction to the plaintiff/petitioner against the defendant on the following terms which we think would meet the ends of the justice and maintain the interests of both sides:-

(1) petitioner would render accounts for six months i. e. July, August, September, October, November and December, 1979, to the Naazar of High Court within four weeks and thereafter within a period of fortnight furnish Bank guarantee for the amount found due by the Naazar.

(ii) respondent should also furnish Bank guarantee within six weeks for Rs, 40,00,000 (Forty lacs)

(iii) current business with effect from 1-1-1980 should continue under the terms of contract.

8. Needless to state that neither the order of the High Court nor the present order is to be considered expression of any opinion on the merits of the case or pleadings and averments of the parties which obviously are still subjudice and will be decided by the High Court after due trial of the case. Learned counsel for the petitioner submitted that the High Court has virtualy decided the main suit against him by passing the impugned order which contains final expression of opinion on various disputed aspects of the case. This is not correct. The view of the High Court was only tentative, being of an interim nature meant for the purpose of issuing or not issuing a temorary injunction and the petitioner will be entitled to persuade the High Court to examine the matter in further detail with reference to the relevant facts and law in the light of the material or any additional material brought or to be brought on record. We have passed the present order just in the interest of both parties to regulate their conduct and dealings ad interim and have left the scope of the whole case as open, as was also the purported intention of the High Court order as well.

9. In the above context it will be just and fair that this case and a cross suit of the defendant on the same subject, which are sub judice in the High Court are decided on preferential basis within a period of six months. Order accordingly. There shall be no order as to costs.

Cited by 40 cases

For educational and research use only — not legal advice. Verify against the official report before relying on it. See our Disclaimer.