ICC (Pvt.) Limited vs Ministry of Energy (Power Division) through Secretary Civil Secretariat, Islamabad and others
The petitioner, a private limited company, challenged the encashment of its bank guarantee (bid security) furnished in response to a tender floated by respondent No.2 for the construction of transmission lines. The petitioner's bid was declared the most advantageous, and a Notification of Award was issued. However, the petitioner failed to furnish the required performance security, demanding a price increase due to escalation. Consequently, the procuring agency encashed the bank guarantee. The High Court dismissed the petitioner's constitutional petition, leading to the present petition for leave to appeal before the Supreme Court. The core legal question was whether a bidder who consents to an extension of the bid validity period can subsequently demand an increase in bid prices, and whether the encashment of the bid security upon failure to furnish performance security was lawful. The Supreme Court held that under the Public Procurement Rules, 2004, a bidder who agrees to extend the bid validity period is bound by the original prices, and any price increase is impermissible at the stage of the award. The Court affirmed that failure to furnish performance security justified the encashment of the bid security, dismissing the petition.
- Whether a bidder who consents to an extension of the bid validity period can lawfully demand an increase in the prices of items originally offered in its bid?
- What are the rights and options available to a bidder under the Public Procurement Rules, 2004 when a procuring agency requests an extension of the bid validity period?
- Can a procuring agency encash a bidder's bank guarantee upon the bidder's failure to furnish the performance security after accepting the Notification of Award?
- Whether the substance of a bid and the prices mentioned therein can be altered during or after an extension of the bid validity period by consent of the parties?
- Rule 16B, Public Procurement Rules, 2004
- Rule 25, Public Procurement Rules, 2004
- Rule 26, Public Procurement Rules, 2004
- Rule 26(3), Public Procurement Rules, 2004
- Rule 26(4), Public Procurement Rules, 2004
- Rule 38, Public Procurement Rules, 2004
- Rule 39, Public Procurement Rules, 2004
JAMAL KHAN MANDOKHAIL, J.---The petitioner is a private limited company that made a bid in response to a tender floated by the respondent No.2 for construction of transmission lines of 132 kV in relation to a 300 MW power project to be set up at Gwadar, Balochistan. The bid was subject to a bid security and validity period as per Rules 25 and 26 of the Public Procurement Rules, 2004 (the "Rules"), respectively. The petitioner furnished a bid bond in the form of a bank guarantee in the amount of Rs.84 million through the respondent No.4 which was valid until 15 August 2021. The initial bid validity period was set to expire on 14 October 2021. The respondent No.2 in exercise of powers conferred upon it by virtue of Rule 26(3) of the Rules further extended the bid validity period till the following dates: 29 October 2021, 13 November 2021, 30 November 2021, and lastly until 13 December 2021. It is necessary to mention here that the extension of each bid validity period was made in writing and for the reasons mentioned therein. All bidders, including the petitioner, had given their consent for the extensions of the bid validity period. Following opening of bids, the respondent No.3 evaluated each bid according to Rule 38 of the Rules and found the petitioner's bid to be most advantageous. Hence, the petitioner was awarded the contract and a Notification of Award ("NOA") was issued in that regard. The petitioner accepted the NOA, however, expressed its concern about the escalation of prices in its reply. On 17 September 2021, the respondent No.3 reminded the petitioner to furnish a performance security in terms of clause 46.1 of the Instructions to Bidders ("ITB") document as the specified time had lapsed. Despite the reminders, the petitioner failed to furnish the performance security. Consequently, on 29 November 2021, upon the request of the respondent No.2 through a letter addressed to the respondent No.4, the petitioner's bank guarantee was encashed. The petitioner challenged the said act of encashment of the bank guarantee through a constitution petition before the High Court of Balochistan at Quetta, which was dismissed vide order dated 17.08.2022, hence, this petition for leave to appeal.
2. The learned counsel for the petitioner contended that the consent for the extensions of the bid validity period were conditional and subject to an increase in the prices of the items earlier offered through its bid. He took the view that the procuring agency was under a legal obligation to undertake an exercise to ascertain the exponential increase in prices between the period of submission and the date of acceptance of the bid. He stated that without following the provisions of the Rules, the act of encashment of the bank guarantee by the respondent No. 2 was unwarranted, illegal, and a blatant abuse of authority.
3. Heard the learned counsel for the petitioner and have perused the record. According to the Rules, the curing agency is under an obligation to process and evaluate the bids within the stipulated bid validity period. However, under exceptional circumstances if an extension of the bid validity period is considered necessary, the procuring agency by exercising powers under Rule 26(3) of the Rules shall for reasons to be recorded in writing, request all bidders for an extension of the bid validity period, provided that such extended period shall not be more than the original or the extended bid validity period. According to sub-rule (4) of the said Rule, it is the prerogative of the bidders to either agree with or to oppose the extension(s) of the bid validity period. In case a bidder does not agree with the request of the procuring agency for an extension of the bid validity period, it shall be allowed to withdraw its bid, without forfeiture of the bid bonds or securities furnished along with bid document. If a bidder agrees to an extension of the bid validity period, it expresses its willingness to undertake the specified task within such extended bid validity period.
The bidder under such circumstances is bound by the commitment and offer already made by it through its bid. Once the bids are finalized by the procuring agency and the bidding evaluation is completed, albeit within the original or extended bid validity period, the procurement contract shall be awarded to the most advantageous bidder in terms of Rule 38 of the Rules; provided that it shall not conflict with any other law, rules, regulations, or government policy. The procuring agency by exercising power under Rule 39 of the Rules shall issue a NOA, requiring the successful bidder to furnish a performance guarantee which shall not exceed 10% of the contract amount. In case the bidder fails to furnish the required performance guarantee, the procuring agency shall proceed as per the Rules.
4. Admittedly, the petitioner agreed to the extension of the bid validity period at all instances sought by the procuring agency. A perusal of the replies submitted by the petitioner reveals that it had simply mentioned its concern regarding the increase in the prices, which cannot be considered as a condition for its consent for the extension of the bid validity period. Even otherwise if such contention of the petitioner is accepted, the Rules do not permit the procuring agency to accept the request of the bidder to increase prices of the items mentioned in the bid at the stage of NOA. This is because Rule 26(4) of the Rules provides that in case of an extension of the bid validity period by consent of the parties, the substance of the bid and the prices of the items mentioned therein, Shall remain unchanged. Had the petitioner been unsatisfied with the prices for undertaking of the specified work after the expiry of the bid validity period it had an option to withdraw its bid, without forfeiture of its bid security. Once the petitioner agreed to perform the specified work on the same terms and conditions and prices as mentioned in the bid document, it is estopped by its conduct of requesting an increase in the prices. Therefore, the respondent No.3 was right in declining the request of the petitioner for the change in the prices, already mentioned in the bid, by correctly following the Rules.
5. As per the Rules, if any bidder is declared successful, it is bound to perform its obligations in terms of its commitment made in the already submitted bid. However, after execution of the contract and during performance of the work, if the bidder claims an increase in the prices it has a remedy under Rule 16B of the Rules. The petitioner's claim is premised on the issue of increase in the prices during the extended bid validity period, without having formally entered into the agreement, furnishing the performance guarantee, or commencing the work as required by the procuring agency. Under such circumstances, the petitioner's request for an increase in the prices made at the time of issuance of the NOA could not be justified. The petitioner's conduct compelled the procuring agency to request the respondent No.4 for encashment of the bid security as provided under the Rules. The learned judges of the High Court after having gone through the record and relevant provisions of the Rules reached the correct conclusion by upholding the decision of the respondent No.2. The learned counsel for the petitioner has not been able to show any point of law of public importance, warranting interference in the judgment impugned.
Thus, for the above reasons, leave to appeal is refused and resultantly, this petition is dismissed.