Pakistan Case Law
1994 CLC 596

ILYAS MARINE AND ASSOCIATES LTD. Versus KARACHI ELECTRIC SUPPLY CORPORATION LTD.

⭐ Prefer in Google
Citation1994 CLC 596
CourtSindh High Court
Case No.Suit No. 250 of 1989
Date1992-11-01
Judge(s)Salahuddin Mirza
ResultOrder accordingly

The plaintiff‑company was sanctioned electric load of 150 KW at its factory premises located at Plot No.E‑13 SITE Karachi. Their electric account number was 77630368 and Consumer No.BH‑36. On 8th July 1985 the company decided to close down its factory due to heavy losses and it requested the defendants to reduce the electric load from 150 KW to 50 KW with immediate effect. After that the Defendants (KESC) made the test report on 21‑9‑1985 and then asked the plaintiff‑company to deposit a sum of Rs.42,326 being the cost of the expenditure involved in the reduction of the load. The plaintiff‑company complied with the demand and deposited the said amount. The load was, however, not changed and the defendants continued to charge the plaintiffs the fixed charges in respect of the electric account even though no charge was being made for the actual use of the electricity a& not a single unit was consumed as the factory was lying closed. The plaintiffs then sent a reminder dated 12‑5‑1986 but in spite of that the load was not changed from 150 KW to 50 KW. The plaintiffs then made a complaint to the Deputy Chief Engineer of the defendants vide their letter dated 6‑7‑1986. Subsequently, a complaint under sections 24 and 26 of the Electricity Act, 1910 was lodged with the Electric Inspector who submitted his report that the billing of fixed charges were, under the circumstances, unjustified and advised the defendant‑company not to bill the fixed charges and refund whatever amount in this regard had been paid by the plaintiff‑company. The defendants did not appeal against the said order of the Electric Inspector which attained finality. The defendants, however, continued to bill the fixed chargers whereupon the plaintiffs complained to the Managing Director of the Defendants vide letter dated 16‑6?1987. After this the defendants made a further demand of Rs.4,500 towards the expenses and even this further demand was duly paid by the plaintiffs. At this stage the defendants filed an appeal under sections 24 and 26 of the Electricity Act on 3‑5‑1987 against the findings of Electric Inspector. According to the plaintiffs this was a belated and time barred appeal, having been filed 109 days after the said findings of the Electric Inspector whereas under Rule 6 of the Electricity Rules, 1937 such appeal can be filed only within three months. This appeal was filed before the Secretary Irrigation and Power Department Government of Sindh. The Deputy Secretary heard the appeal ex parte and remanded the case to Electric Inspector for fresh decision vide order dated 23‑7‑1987. According to the plaintiffs this remand was illegal and unjustified under the circumstances of the case. The Electric Inspector then heard the case again and now vide order dated 20‑10‑1987 held that as the written consent for change in supply from 150 KW to 50 KW was given by the plaintiffs in February 1986, the defendants should have finalised the case within a reasonable time. He also opined that the plaintiffs were being unnecessarily penalised through billing of the fixed charges. He, therefore, recommended that the change of tariff should be allowed from 9‑3‑1986, that is, one month after the acceptance of the written consent of the plaintiff‑company. On the basis of this recommendation the defendants vide their letter dated 16‑2‑1988 conveyed to the plaintiffs their approval to refund the excess amount paid by the plaintiffs in accordance with the advice of the Electric Inspector. The plaintiffs, however, felt aggrieved from the findings of the Electric Inspector dated 20‑10‑1987. The plaintiffs then preferred appeal to the Secretary Government of Sindh who, however, dismissed the appeal vide order dated 12‑4‑1988 and upheld the order of Electric Inspector dated 20‑10‑1987. The plaintiffs feel aggrieved from the remand order passed by the Deputy Secretary on 23‑7‑1987 and from the order of the Electric Inspector dated 20‑10‑1987 and from the further order passed by the Secretary, on the appeal filed by the plaintiffs, dated 12‑4‑1988. The case of the plaintiff‑company is that their sanctioned load should have been reduced from 150 KW to 50 KW within reasonable time of their making a request therefor and the billing of the fixed charges for 150 KW load for the subsequent period are unjustified when the delay was cause‑Tat the instance of defendants themselves and it is an admitted position that the factory was lying closed and no charges had been made for electric consummation since no electricity was used during this period. The plaintiffs, therefore, seek the payment of Rs.1,49,969.74 with 14% interest from the date of the institution of the suit till realisation. The defendants contested the suit and filed their written‑statement. A bald objection was made that the suit was not maintainable but it was not disclosed as to why and under what law it was not maintainable. On facts it was stated that the advice for reduction of the load was received from the Meter Department on 23‑5‑1987 and, therefore, the reduction of load was allowed from this date. They, however, did not explain as to' why and under what circumstances the Meter Department submitted its advice on 23‑5‑1987 when the application for the reduction of the load was given on 8th July 1985 and the Test Report as demanded by the. defendants had been submitted by 21‑9‑1985.

2. On these pleadings the following consent issues were adopted by the Court:‑‑

"(1) ????? Whether the Defendant‑Company extensively delayed the request for reduction of their electric load from 150 KW to 50 KW in spite of the Plaintiffs' Application dated 8th July 1985? '

(2) ??????? Whether even after the decision of the Electric Inspector dated 14‑1‑1987, the Defendant‑Company kept on billing for fixed charges, was mala fide?

(3) ??????? Whether the payment of demand notices of Rs.42,326 and Rs,4,500 to the Defendant‑Company was justified?

(4) ??????? Whether the Defendant‑Company delayed the reduction of load till August 1987 with ulterior motives in violation of Schedule VI(1) & (X) (1) of the Electricity Act?

(5) Whether the Secretary, Irrigation & Power Government of Sindh was competent to hear the time barred appeal of the Defendant?Company?

(6) ??????? Whether the Plaintiff‑Company is entitled for refund of fixed charges paid by them since July 1985?

(7) ??????? Whether the Defendant‑Comp4ny has miscalculated the amount refundable to the plaintiff‑Company?

(8) ??????? Whether there were any dues outstanding against the Plaintiff Company as allegedly deducted by the Defendant‑Company?

(9) ??????? Whether the Plaintiff‑Company is entitled for the claim prayed for?

(10) What should the decree be?

3. ???????? My findings on the above issues are as follows:‑‑

4. ISSUE No.1 . Exh.5/2 is the letter dated 8‑7‑1985 whereby the plaintiff‑company desired the reduction of the electric load from 150 KW to 50 KW. It is a short letter and is quoted below:‑‑

"Having incurred heavy losses we have decided to close our factory,

We have a contracted load of 150 KW, we request you to reduce it to 50 KW immediately."

In para. 2 of the written‑statement the defendants admit the receipt of this letter. It is further stated by the plaintiffs in para. 4 of the plaint that as desired by the defendants, they (the plaintiffs) submitted the "Test Completion Report" on 21‑9‑1985 which is Exh.5/3. The defendants did not deny this fact in their written‑statement and their witness D.W.1 Azam Panwar admitted this in his examination‑in‑chief. However the defendants added that on 14‑3‑1987 they had issued Demand Notice for Rs.42,326. The date "14‑3‑1987" appears to be incorrectly given by the defendants in their written‑statement because this Demand Note (or Power Quotation as it is styled) is Exh.5/4 and the issue date given over it is "3‑5‑1986" and it was valid up to 2‑8‑1986 for payment which date was extended up to 15‑1‑1987. The date of payment of this amount is not clearly stamped by the bank accounting machine but it must be before 15th January 1987. The plaintiffs state that ‑the reason of this delay in the payment was that according to them this demand was exorbitant and they were demanding its reduction but the defendants did not reduce it and eventually ? they got the validity of the demand extended up to 15‑1‑1987 and paid it before that time. However, the needful was still not done and another Demand Notice for Rs.4,500 was issued on 14‑7‑1987 which was also paid on 15‑12‑1987. However, the defendants took another eight months and the load was reduced in August 1987. During all this period the defendants continued to charge Rs.8,588 by way of fixed charges. These fixed charges were payable on 150 KW load and they were in addition to the charges for the electricity consumed as per meter (It is admitted position that the factory had been closed in July 1985 and, therefore, electric charges as per meter were Zero but the plaintiffs were being charged "fixed charges" nevertheless until August 1987.

5. It is evident that the defendants delayed the action on the request of the plaintiff‑company for the reduction of the load. Immediately on receiving the request of plaintiffs for reduction of the load as per Exh.5/2 on 08th July 1985 the defendants should have issued the demand notice at the latest by the end of the month or if they wanted any test report, they should have intimated the plaintiffs in that regard within the same time. It is, however, evident that the defendants slept over the matter and took no action and it was only when the plaintiffs personally approached them that on oral demand test report was made. Even so the test report (Exh.5/3) was submitted on 21‑9‑1985. Since the reduction of the load would have saved the plaintiffs from paying the fixed monthly charges it was the duty of the defendants to have taken action on Exh.5/2 on 08th July 1985 itself so that all formalities were completed within a month. At any rate delay after submission of test report (21‑9‑1985) is not justified in any case. When the D.W‑1 Azam Aanwar Dy. Chief Controller (Billing) of KESC was asked to explain the delay, his answer was "I cannot say". This was an admission on his part that the delay was unjustified.

6. I ? would, therefore, hold that the ? defendant‑company caused unnecessary delay in meeting the request of the plaintiff‑company. The issue is, therefore, decided in the affirmative. I may here also add that since the load was required to be reduced, there was no necessity of any test report and it was A also unnecessarily demanded by the defendants.

7. ISSUE No.2 : ---‑After the decision of the Electric Inspector dated 14‑1‑1987, the defendants had only two alternatives ‑‑‑‑ either to appeal to Secretary Irrigation or to comply with the decision. As such, it was not only mala fide but illegal on the part of the defendants to keep on billing the plaintiffs with the "fixed charges". Issue decided accordingly.

8. ISSUE No.3 .‑‑‑When a consumer is getting certain load and he wants to increase it, it may require strengthening the supply lines/cables and other equipment and this may require expenditure but when a customer wants the reduction of load, it does not require any expenditure. The supply line/cables and other equipment which are fit enough for higher load can take the lesser load without any difficulty. There is nothing on record to sustain the charges of Rs.42,326. There is even less justification for a subsequent demand of Rs.4,500 vide Exh.5/5. The issue is decided accordingly.

9. ISSUE No. .‑‑‑The defendants could not justify the delay from July 1985 to August 1987. Their witness was totally blank on the point of delay. Under the circumstances, the only inference which can be drawn is that the delay was in violation of the Schedule of the Electricity Act and was due to sheer inefficiency or callousness on the part of the defendants. The issue is 8 decided accordingly.

10. ISSUE No.5 .‑‑‑Complaint filed by the plaintiffs under sections 24 and 26 bf the Electricity Act was decided by the Electric Inspector on 14th January 1987 (Ex.5/13). Copy of the decision was duly sent to the defendants as endorsement thereon shows. Under Rule 6‑B of Electricity Rules, 1937, the defendants could appeal to Secretary Irrigation and Power Department Government of Sindh within three months. Since no appeal was preferred within this time, Deputy Secretary (Power) Government of Sindh vide his letter dated 29th April 1987 (Exh.5/14) directed the defendants to comply with the decision of the Electricity Inspector. It was after this that the defendants preferred appeal to the Secretary on 3‑5‑1987 as per averment in para. 11 of the plaint. It was, therefore, clearly barred by time. It was in para. 11 of the plaint that the plaintiffs had raised this issue of limitation. In para. 8 of their written‑statement the defendants replied that the appeal was filed in time but no date of filing of appeal was given nor copy of the appeal was filed. Even in evidence, not a single word was said by their witness‑nor copy of the appeal was filed to show that it was filed in time. The defendants have not filed even copy of the Appellate Order. Averment made by the plaintiffs in this regard goes unrebutted and I would hold that the appeal was filed on 3‑5‑1987 and thus it was a time‑barred appeal and Secretary Power and Irrigation committed serious error in entertaining it. He was not competent to hear time‑barred appeal. The issue is, therefore, decided in the negative. .

11. Besides, the plaintiffs had also pleaded in para. 11 of the plaint that the Secretary Power and Irrigation had ex parte entertained this appeal and had also decided it ex parte but this allegation was not denied in the written? statement and shall therefore be deemed to be admitted.

12. ISSUE No.6 .‑‑‑Strictly speaking, the defendants should not have billed "fixed charges" after receiving the request of the plaintiffs for the reduction of the load vide Exh.5/2. I would, however, allow grace period of two months f (July and August 1985) and would hold that the defendants were not entitled to charge the "fixed charges" after 30th August 1985 and should refund the same. Issue decided accordingly.

13. ISSUE No.7 .‑‑‑The calculations given by the plaintiffs in para. 16 of the plaint were not denied by the defendants. Even so, the calculations have been checked and are found to be correct. However, in view of the finding under Issue No.6, fixed charges for July and August 1905 amounting to Rs.17,170 will be deducted from the total of Rs.1,49,969.74, which gives Rs.1,32,799.74. The issue is decided accordingly.

14. ISSUE No.8 .‑‑‑This issue does not arise out of the pleadings of the parties and is, therefore, cancelled.

15. ISSUE No.9 : ---In view of my findings under Issue No.5, the decision of the Electric Inspector dated 14‑1‑1987 (Exh.5/13) holds the field. As such, the order of remand dated 23‑7‑1987 passed by the Secretary Power & Irrigation and the subsequent order passed by the Electric Inspector on 20‑10?1987 and the subsequent order of the Secretary Power & Irrigation dated 12‑4?1988 (Exh.5/15) are all void and illegal. The plaintiff‑company is, therefore, D entitled to the claim as per decision Exh.5/13 and in addition to that the plaintiff‑company is also entitled to the refund of Rs.42,326 and Rs.4,500 vide findings under Issue No.3. The issue is, therefore, decided in the affirmative.

16. ISSUE No.10 .‑‑‑In view of the above findings the suit is decreed with costs in the sum of Rs.1,49,969.74. The plaintiffs are also held entitled to interest @ 14% from the date of the suit till the realisation of the decretal amount.

17. Since it is a clear case of negligence and callousness on the part of certain members of the staff of the defendants, the defendants may look into the desirability of holding an enquiry and fixing the responsibility and recovering the decretal amount from them in proportion of their part in the delay from 1st September 1985 to August 1987.

AA./1‑232/K ?????????????????????????????????????????????????????????????????????????? ??????????? Order accordingly.

Cited by 1 case

For educational and research use only — not legal advice. Verify against the official report before relying on it. See our Disclaimer.