Pakistan Case Law
1999 CLC 26

Messrs TAUSEEF CORPORATION (PVT.) LTD., LAHORE vs LAHORE DEVELOPMENT

⭐ Prefer in Google
Citation1999 CLC 26
CourtLahore High Court
Case No.Intra-Court Appeal No.568 of 1998
Date1998-07-17
Judge(s)Raja Muhammad Khurshid and Kh. Muhammad Sharif
ResultAppeal dismissed
AI Summary — generated from this judgment; read the full text below and verify before relying on it.

This Intra-Court Appeal challenged a judgment dismissing writ petitions filed against the termination of a construction contract by the Lahore Development Authority. The appellants argued that the unilateral cancellation of the agreement was illegal, mala fide, and without jurisdiction, invoking the principle of locus poenitentiae, as they had already taken decisive steps by commencing construction. The core legal question was whether the High Court's extraordinary writ jurisdiction could be invoked to enforce a contract or challenge its termination when alternative remedies existed. The Court held that the writ petitions were not maintainable because the appellants had access to efficacious and effective alternative remedies, specifically arbitration or a civil suit for damages. The Court affirmed that disputes arising from contractual liabilities, which are dependent on the personal volition of parties, cannot be specifically enforced through writ jurisdiction. Furthermore, the Court emphasized that where a contract contains an arbitration clause, that forum must be utilized. Consequently, the appeal was dismissed in limine, upholding the Single Judge's decision that the matter fell within the plenary jurisdiction of the Civil Court.

Questions settled in this judgment
  • Can the extraordinary writ jurisdiction of the High Court be invoked to enforce a contract or challenge its termination when alternative remedies like arbitration or civil suits are available?
  • Does the principle of locus poenitentiae prevent a public authority from cancelling an agreement after the other party has taken decisive steps in performance of the contract?
  • Is a contract dependent on the personal volition of parties specifically enforceable through writ jurisdiction?
Laws & provisions referred
  • Section 3, Law Reforms Ordinance 1972
  • Section 21(a), Specific Relief Act 1877
writ jurisdictioncontractual disputelocus poenitentiaearbitration clausealternative remedyspecific performanceintra-court appeal

ORDER

This Intra-Court Appeal is preferred under section 3 of the Law Reforms Ordinance, 1972 against the judgment, dated 18-2-1998 passed in Writ Petition No.4113 of 1997 and Writ Petition No. 12339 of 1997 by a learned Single Judge of this Court.

2. The detail of facts has already been given in the impugned judgment which need not to be reproduced to avoid repetition. The writ petitions mentioned above were brought against the action taken by respondent No. l whereby, the construction work was stopped at the site in June, 1995. The matter having been raised at different forums, finally the contract between the parties was terminated on 20-2-1997. That termination was challenged in the writ petitions aforementioned on the ground that cancellation of a lawful agreement through unilateral action was illegal, mala fide and without jurisdiction. In this context, it was contended that the agreement was wrongly cancelled by the respondents on the ground that the then Chief Traffic Engineer, TEPA, L.D.A. Had entered into the agreement without lawful authority and as such, the same was void ab initio. Hence it was alleged that this plea was not open to the respondents for cancellation of the agreement because the same was executed on their behalf by their former Chief Traffic Engineer and if there was any flaw in his powers of which he was vested, the delinquent department could not take advantage of their own in-competency in making appointment of unauthorised person to enter into public agreement. Besides that, the principle of locus poenitentiae (power of re-calling till decisive steps taken), prevented the respondents to retrieve or recall the agreement as the decisive steps had already been taken by the aggrieved party i.e. Appellants by acting upon the agreement and in pursuance of the same, the first floor was completed, hence the powers available to the respondents to cancel the agreement had come to an end after the decisive steps had been taken by starting the construction of the plaza by the appellants in pursuance of the agreement. In addition to that, it was urged that the writ petitions were competent because agreement was entered into between the parties under statutory provisions and as such, would be enforceable at law irrespective of the provisions contained in section 21(a) of the Specific Relief Act.

3. We have considered the foregoing points which have been discussed in detail by the learned Single Judge in his judgment. It is true that the work on the I agreement had started but admittedly the same was stopped in June, 1995. However, the appellants remained silent over stoppage of the work till the agreement was finally cancelled by the respondents on 20-2-1997 by addressing the impugned letter. In that situation, the delay on the part of the appellants would be relevant for seeking the discretionary relief under the extraordinary jurisdiction of writ petition. Even otherwise, the alleged loss suffered by the appellants due to termination of contract could be claimed in the form of damages for which a separate remedy under the normal law was available and could be invoked. In addition to that, the construction work which is dependent on the personal volition of the parties cannot be specifically enforced in its substantive terms in case of its breach. The only remedy provided for such breach of contractual liability entailed the incident of damages falling purely within the ambit of civil action under the plenary jurisdiction of Civil Court. Lastly, the agreement itself contained a clause for arbitration whereby the differences of opinion between the parties or any dispute arising out of the impugned agreement could be referred to an arbitrator for settlement instead of bringing legal action. It is, thus, obvious that an efficacious and effective remedy was available to the appellants in the form of arbitration or civil action under the normal law. The writ jurisdiction in such a situation could not be invoked. The impugned judgment passed by the learned Single Judge being unexceptionable does not call for interference in this appeal.

The same is accordingly dismissed in limine.

Cited by 6 cases

For educational and research use only — not legal advice. Verify against the official report before relying on it. See our Disclaimer.